Trenching and excavation JHA example
Trench collapses kill workers every year, and most of those deaths are preventable. Here's what a trenching JHA should cover, with a short example you can compare yours against.
Key rules a trenching JHA should reflect
- Protective systems at 5 feet. Trenches 5 ft or deeper need sloping, benching, shoring or a trench box unless they're entirely in stable rock. Deeper than 20 ft, the system must be designed by a registered professional engineer (OSHA 1926.652; Cal/OSHA Title 8 §1541.1).
- A competent person inspects the excavation daily before work starts, after rain and as conditions change, and pulls the crew out when there's a hazard (OSHA 1926.651(k)).
- A way out: a ladder or other exit within 25 ft of workers in trenches 4 ft or deeper (1926.651(c)(2)).
- Spoils and equipment at least 2 ft back from the edge (1926.651(j)(2)).
- Utilities located first: call 811 (DigAlert in Southern California, USA North 811 in Northern California) at least two working days before you dig, and pothole by hand near marks.
- Hazardous air tested where it could be present, such as near sewers, landfills or fuel lines.
- In California, a Cal/OSHA permit is required for trenches and excavations 5 ft or deeper that workers enter.
Example JHA (short version)
| Job step | Hazards | Controls | RAC |
|---|---|---|---|
| 1. Locate utilities and lay out the trench | Striking a buried gas or electric line; traffic at the work zone | Valid 811 ticket on site; marks reviewed with the crew; hand-dig or vacuum-excavate within the tolerance zone; cones and signs per the traffic plan | M |
| 2. Excavate the trench | Cave-in; struck by the excavator's swinging counterweight; spoils sliding back in | Trench box or shoring before anyone enters at 5 ft+; swing-radius barricade; spoils kept 2 ft back; competent person inspects before entry and after rain | H |
| 3. Work in the trench (pipe, bedding, connections) | Cave-in; caught under a suspended pipe; hazardous air near a live sewer | Work only inside the protective system; ladder within 25 ft; tag lines, nobody under the load; air tested before entry and monitored | H |
| 4. Backfill and compact | Struck by loader or compactor; vibration and noise | Spotter for backing equipment; workers stay clear of the bucket; hearing protection; remove the box in lifts as backfill rises | M |
A real JHA for your job would add the site details: trench depth and soil type, nearby structures or footings, traffic control, dewatering and the equipment list with training and inspections.
Make yours in minutes
Paste your scope of work and the JHA Builder writes a site-specific JHA: job steps, hazards, controls, risk ratings and Cal/OSHA and OSHA references, as a PDF ready for your GC or a Word file you can edit.
Start your 7-day free trialMore examples: all JHA examples · how to write a JHA