Activity Hazard Analysis (AHA) for USACE and federal jobs

On U.S. Army Corps of Engineers (USACE) jobs, and on many NAVFAC and other federal contracts, the hazard analysis is called an AHA and follows the EM 385-1-1 safety manual. It has a few requirements a commercial JHA often doesn't.

When you need an AHA

Under EM 385-1-1, the contractor prepares an AHA for each definable feature of work (DFOW): a distinct phase of the work such as site clearing, excavation, concrete placement or roofing. The AHA is reviewed and accepted by the government before that work starts, and it is reviewed with the workers doing it. Your contract's Accident Prevention Plan (APP) will say how AHAs are submitted on your project.

What an AHA includes

  • Job information: contract, project, activity, location, contractor, who prepared it and when.
  • Definable feature of work the AHA covers.
  • Work steps in the order they happen.
  • Hazards for each step, specific to the work and the site.
  • Controls for each hazard.
  • Risk Assessment Code (RAC) for each step, and an overall RAC.
  • Equipment to be used, with the inspection requirements and training requirements for each.
  • Competent and qualified persons by name for the activities that need them.
  • Signatures: who prepared it, who reviewed it, and acceptance of the risk.

How the RAC works

The RAC combines probability (frequent, likely, occasional, seldom, unlikely) with severity (catastrophic, critical, marginal, negligible) into E, H, M or L. Each step is rated with the controls in place, and the overall RAC on the cover is the highest of those. Higher overall risk has to be accepted by someone with the authority set out in the project's APP, so the AHA should leave room for that signature.

SeverityFrequentLikelyOccasionalSeldomUnlikely
CatastrophicEEHHM
CriticalEHHML
MarginalHMMLL
NegligibleMLLLL

Common reasons federal reviewers send AHAs back

  • One AHA trying to cover the whole contract instead of each definable feature of work.
  • Equipment listed without its inspection and training requirements.
  • Competent or qualified persons not named, or one person named for roles that must be different people.
  • No hold points: who releases high-risk phases (for example the next excavation lift or removing shores) and what record they check.
  • Rescue plans that stop at "call 911" for falls, confined spaces or work over water.

Make yours in minutes

Paste your scope of work and the JHA Builder writes a site-specific AHA in the EM 385-1-1 format: job steps, hazards, controls, risk ratings and Cal/OSHA and OSHA references, as a PDF ready for your GC or a Word file you can edit.

Start your 7-day free trial

The JHA Builder switches to the AHA format automatically when your scope mentions USACE, EM 385-1-1 or NAVFAC. See also how to write a JHA.

Common questions

Is an AHA the same as a JHA?

It's the same idea in the federal format. An AHA under EM 385-1-1 adds the definable feature of work, a RAC for every step and overall, an equipment table with inspection and training requirements, named competent and qualified persons, and risk acceptance.

Who accepts the AHA?

The government reviews and accepts it before the work starts, and the person with authority under your project's Accident Prevention Plan accepts the residual risk. Check your contract and APP for the exact process.