Electrical work JHA example
Electrical work mixes shock and arc flash with ordinary construction hazards like ladders, lifts and overhead work. Here's what an electrician's JHA should cover.
Key rules an electrical JHA should reflect
- Work de-energized whenever possible. Before working on de-energized equipment, an authorized person notifies everyone involved, opens and locks out the disconnects, tags them and tests that the circuit is dead (Cal/OSHA Title 8 §2320.4; federal OSHA 1926.417).
- Energized work only when supervision decides it's needed, and only by workers instructed in the techniques and hazards (§2320.2). Your JHA should say who makes that call and what PPE and procedures apply.
- Re-energizing: confirm everyone is clear, and locks and tags come off only by the person who put them on (§2320.5).
- GFCI on temporary power: 120-volt, 15- and 20-amp receptacles used by workers on construction sites need ground-fault protection (Title 8 §2405.4; OSHA 1926.404(b)(1)).
- Ladders near electrical work: no metal or conductive ladders where they could contact energized parts.
Example JHA (short version)
| Job step | Hazards | Controls | RAC |
|---|---|---|---|
| 1. Plan the work and identify energy sources | Unknown feeds or backfed circuits; working on the wrong circuit | Review drawings and panel schedules; walk down the circuits with the superintendent; identify every source including generators and solar | M |
| 2. Lock out, tag and verify zero energy | Shock or arc flash from a circuit thought to be off | Each worker applies their own lock and tag; test the meter on a known live source, test the circuit, then retest the meter | H |
| 3. Install conduit, boxes and supports | Falls from ladders or lifts; drilling into hidden utilities; overhead drops | Correct ladder for the height, non-conductive near electrical; scan before drilling; tool lanyards and barricade below | M |
| 4. Pull wire and make terminations | Hand injuries from pulling equipment; contact with adjacent energized parts | Puller rated for the pull and anchored; gloves; insulate or cover adjacent energized parts; stay inside the locked-out boundary | M |
| 5. Energize and test | Shock or arc flash during first energization; people working downstream | Notify all trades; confirm everyone is clear; only the person who locked out removes their lock; stand to the side of the disconnect | H |