Demolition hazards often hide inside the structure: weakened framing, live utilities, asbestos and lead. A demolition JHA starts with what the survey found and builds the steps around it.
Key rules a demolition JHA should reflect
- A written engineering survey of the structure before demolition starts, kept on the job site for the whole project (Cal/OSHA Title 8 §1734; federal OSHA 1926.850(a)). Deficiencies the survey finds are shored or braced first (§1735).
- Utilities shut off, capped or controlled before work starts (1926.850(c)).
- Asbestos and lead identified before disturbing materials (Title 8 §1529 and §1532.1). In California, demolition of many structures also needs a Cal/OSHA permit.
- Dust control with water to keep material and debris wet (§1735), plus silica controls for concrete and masonry (§1532.3).
- No walking across exposed floor joists, beams or girders (§1735).
Example JHA (short version)
| Job step | Hazards | Controls | RAC |
|---|---|---|---|
| 1. Survey and plan | Unplanned collapse; hidden asbestos, lead or live utilities | Written engineering survey on site; asbestos and lead survey results reviewed with the crew; sequence planned top-down | H |
| 2. Shut off and verify utilities | Gas leak, electrocution or flooding from live lines | Utilities disconnected by the owner or utility and verified; lines capped; lockout where the contractor controls the shutoff | H |
| 3. Interior strip-out | Asbestos or lead exposure; falls through floor openings; cuts and punctures | Abatement complete before general demo; openings covered or guarded; gloves, eye protection, debris chutes | M |
| 4. Structural demolition | Struck by collapsing structure or falling debris; equipment rollover | Exclusion zone barricaded; work top-down per the survey; equipment on firm, level ground with the operator's view clear | H |
| 5. Debris handling and dust control | Silica dust; struck by loaders and trucks | Wet down material continuously; respirators where the silica plan requires them; spotters for backing equipment | M |